NOOR PV 1

The NOOR PV I Programme will consist of three projects: NOOR Ouarzazate IV with a capacity of 72 MW, NOOR Laayoune, 85 MW and NOOR Boujdour 20 MW. ACWA Power submitted the lowest tariff price for the project at 4,6MADc/kWh, i.e. 4.8$c/kWh.

 

Together, the NOOR PV I Programme and the NOOR Ouarzazate I, II and III CSP projects demonstrate the viability of all solar technologies, and advance the Moroccan Kingdom’s ambition to install two gigawatts of solar energy by 2020.

 

Construction on NOOR PV I will begin in Q1 2017 and is estimated to take 12 months to complete.

 

The plants will produce enough electricity to power thousands homes every year, using photovoltaic (PV) solar panels to generate electricity.  It is estimated that the project will also reduce carbon emissions by tens of thousands of tons of CO2, equivalent emissions for every year of operation. 

 

ACWA Power contributes to the expansion of the grid in Morocco, by building a 26 km High Voltage (225 kV) line to connect NOOR Laayoune and a 12 km Medium Voltage (22 kV) line to connect NOOR Boujdour.

 

Click here for NOOR Laayoune location

Click here for NOOR Boujdour location

Click here for NOORo IV location

KEY FACTS

  • LOCATION
    Ouazazate, Morocco
  • OFFTAKER
    Masen (Moroccan Agency for Sustainable Energy)
  • POWER NOOR OUARZAZATE IV
    55 MWe
  • POWER NOOR LAAYOUNE
    65 MWe
  • POWER NOOR BOUJDOUR
    15 MWe
  • CONFIGURATION
    Photovoltaic (PV)
  • COD
    Q1 2018
  • OFFTAKE CONTRACT
    PPA-BOT–20 YR
  • EPC
    Chint Group, Sterling & Wilson and Shapoorji Pallonji
  • PROJECT COST
    USD 210 Mn
  • ACWA POWER SHARE
    75.00%